From Napier grass to compressed biogas
Feedstock → pre-treatment → slurry → anaerobic digestion → raw biogas → H₂S removal → CO₂ upgrading → drying → compression → CBG filling. With digestate recovered as organic manure.
The integrated CBG process
Explore each stage of the gas pathway and the digestate pathway, as configured in our flagship plant's Detailed Project Report.
Feedstock harvesting & receipt
Napier grass is harvested and brought to the plant, supplemented by other organic feedstock under the multi-feedstock design. The design basis is 115 TPD at 25% total solids.
Plant block diagram
How material and gas move through the plant, with design values from the 5 TPD project. Animated lines show the gas, feedstock and digestate streams.
What happens at each stage
Concise technical notes for each step of the gas pathway.

Feedstock harvesting & receipt
Napier grass is harvested and brought to the plant, supplemented by other organic feedstock under the multi-feedstock design. The design basis is 115 TPD at 25% total solids.
Chopping, grinding & conveying
Grass is chopped and ground to reduce particle size, increasing the surface area available to microorganisms, then conveyed to slurry preparation.
Slurry preparation
Prepared biomass is mixed with process liquid — including recirculated liquid from digestate separation — to form a pumpable slurry fed to the digester.
Mesophilic anaerobic digestion
A single 10,000 m³ continuously stirred tank reactor (CSTR) digests the slurry under mesophilic conditions with a hydraulic retention time of approximately 36 days.
Raw biogas collection
Biogas is collected from the digester headspace. Design production is 11,900–13,200 Nm³/day at 55–60% methane, the balance being mainly CO₂ with traces of H₂S and moisture.
Hydrogen sulphide removal
Water washing / scrubbing and iron oxyhydroxide media remove H₂S, protecting compressors and pipework from corrosion.
CO₂ removal & methane upgrading
Chilled-water scrubbing or two-stage membrane technology separates CO₂, upgrading the gas to at least 98% methane.
Gas drying
A desiccant dryer with heatless regeneration removes moisture to the dew point required for high-pressure storage.
High-pressure compression & odourisation
Reciprocating compressors raise the gas to a design pressure of up to 250 bar. The gas is odourised so that any leak can be detected by smell.
CBG cascade filling & dispatch
Compressed biogas is stored and dispatched through cascade filling. PLC/SCADA and online gas analysers monitor quality throughout.
Mesophilic CSTR digestion
A continuously stirred tank reactor keeps feedstock, microorganisms and temperature uniform throughout the tank. Our flagship design uses a single 10,000 m³ CSTR in the mesophilic range with a hydraulic retention time of approximately 36 days.

Gas cleaning, upgrading and compression
The purification configuration specified in the DPR. These technologies are supplied by specialist technology partners and are not proprietary to Deva Bio Engineering.
H₂S removal
Water washing / scrubbing with iron oxyhydroxide mediaHydrogen sulphide is removed early in the gas train to protect downstream equipment from corrosion and to meet CBG quality limits.
CO₂ removal & methane upgrading
Chilled-water scrubbing or two-stage membrane separationCarbon dioxide is separated from the gas stream to raise methane content from 55–60% in raw biogas to at least 98% in the product gas.
Gas drying
Desiccant dryer with heatless regenerationMoisture is removed so the gas meets dew-point requirements before high-pressure compression and storage.
High-pressure compression
Reciprocating compressor, design up to 250 barUpgraded gas is compressed in stages for cascade storage and dispatch as compressed biogas.
Automation & gas quality
PLC / SCADA with online gas quality monitoringProcess parameters and product gas composition are monitored continuously for stable, safe and documented operation.
Product gas
≥ 98% CH₄ · up to 250 bar · odourisedThe result is compressed biogas suitable for cascade storage and dispatch, monitored continuously by online gas analysers.
High-pressure compression and cascade filling
Dried, upgraded gas is compressed by reciprocating compressors to a design pressure of up to 250 bar, odourised, and stored in cylinder cascades from which CBG is dispatched.

Digestion → separation → FOM / LFOM
Digestate leaving the CSTR is separated into solid and liquid fractions.
- Digestate discharge — Digested material leaves the CSTR as digestate, containing undigested fibre, nutrients and process water.
- Solid–liquid separation — Digestate is mechanically separated into a solid fraction and a liquid fraction.
- Fermented Organic Manure — The solid fraction is recovered as Fermented Organic Manure (FOM) for soil application after conditioning.
- Liquid Fermented Organic Manure — The liquid fraction (LFOM) is partly recirculated to slurry preparation and partly available as a liquid organic nutrient.
Actual FOM and LFOM quantities and their marketable quality depend on feedstock, plant operation and final product specifications, including applicable fertiliser regulations.
The 14 integrated steps
As listed in the Detailed Project Report for the 5 TPD CBG plant.
- Napier grass harvesting and preparation
- Grass chopping and grinding
- Feedstock conveying
- Slurry preparation
- Anaerobic digestion through a mesophilic CSTR
- Raw biogas collection
- H₂S removal
- CO₂ removal and methane upgrading
- Gas drying
- High-pressure compression
- Odourisation
- CBG cascade filling
- Digestate solid–liquid separation
- FOM and LFOM recovery
Planning a biogas or CBG project?
Share your feedstock, location and the capacity you have in mind. We'll discuss how an integrated biogas plant could be configured for your requirement.