Flagship project

5 TPD Compressed Biogas Project – From Napier Grass to Renewable Energy

A proposed integrated compressed biogas plant designed to convert Napier grass and other organic feedstock into up to 5,000 kg/day of CBG, with fermented organic manure recovered from the digestate.

Proposed · Under Development Shivni, Taluka Beed, District Beed, Maharashtra
5,000kg/day
Rated CBG capacity (up to)
115TPD
Design feedstock at 25% TS
10,000m³
Single CSTR digester
≥98% CH₄
CBG methane purity
up to 250bar
Compression design
~36days
Hydraulic retention time

Proposed project. Technical figures are design values from the Detailed Project Report and the supplier's techno-commercial offer, and remain subject to final engineering, approvals and contractual confirmation.

Project overview

Renewable gas from Napier grass in Beed

Deva Bio Engineering Private Limited is developing a compressed biogas plant at Shivni, Taluka Beed. The plant is designed around Napier grass as its primary feedstock, with multi-feedstock capability, and a rated output of up to 5,000 kg of CBG per day over 330 operating days a year.

Harvested grass is chopped, ground and made into slurry, then digested in a single 10,000 m³ mesophilic CSTR. The raw biogas is cleaned of H₂S, upgraded by removing CO₂, dried, compressed to a design pressure of up to 250 bar, odourised and dispatched through cascade filling. Digestate is separated into fermented organic manure (FOM) and liquid fermented organic manure (LFOM).

Project status: proposed / under development. This page describes the plant's design basis. It is not yet constructed or operational, and figures remain subject to final engineering, approvals and contractual confirmation.

At a glance

Feedstock
Napier grass / multi-feedstock
Digester
1 × 10,000 m³ CSTR
CBG output
Up to 5,000 kg/day
Operation
330 days/year
Location
Shivni, Beed
View Shivni, Beed on Google Maps
Technical configuration

Plant specification

Design parameters from the Detailed Project Report and the supplier's techno-commercial offer.

Lush green Napier grass cultivation used as energy crop feedstock
5 TPD CBG plant technical specification
Project
DeveloperDeva Bio Engineering Private Limited
Proposed locationShivni, Taluka Beed, District Beed, Maharashtra
Project statusProposed / under development
Operating basis330 days per year
Feedstock
Primary feedstockNapier grass / multi-feedstock
Design feedstock input115 TPD at 25% total solids
Digestion
Digester1 × 10,000 m³ CSTR (continuously stirred tank reactor)
Process temperature regimeMesophilic
Hydraulic retention timeApproximately 36 days
Biogas
Raw biogas production (design)11,900 – 13,200 Nm³/day
Raw biogas methane content55 – 60%
CBG
Rated CBG outputUp to 5,000 kg/day
CBG methane purityAt least 98%
Compression design pressureUp to 250 bar
DispatchOdourised CBG via cascade filling
By-products
Digestate handlingSolid–liquid separation into FOM and LFOM
Execution
Indicative equipment delivery36 – 42 weeks (supplier estimate, subject to conditions)
Process

Napier grass to CBG — the plant process

The complete integrated process, followed by the plant block diagram.

Gas pathway Digestate pathway
Stage 1 of 10

Feedstock harvesting & receipt

Napier grass is harvested and brought to the plant, supplemented by other organic feedstock under the multi-feedstock design. The design basis is 115 TPD at 25% total solids.

  • Napier grass harvesting
  • Multi-feedstock flexibility
  • Weighbridge & storage
Digestate pathwaybranches from stage 04 · Digestion
Digestate dischargeDigested material leaves the CSTR as digestate, containing undigested fibre, nutrients and process water.
Solid–liquid separationDigestate is mechanically separated into a solid fraction and a liquid fraction.
Fermented Organic ManureThe solid fraction is recovered as Fermented Organic Manure (FOM) for soil application after conditioning.
Liquid Fermented Organic ManureThe liquid fraction (LFOM) is partly recirculated to slurry preparation and partly available as a liquid organic nutrient.
Napier grass to compressed biogas — process block diagramNapier grass is chopped and ground, made into slurry and fed to a 10,000 cubic metre mesophilic CSTR digester. Raw biogas passes through H2S removal, CO2 upgrading, drying, compression with odourisation and cascade filling as CBG. Digestate is separated into FOM and LFOM, with LFOM recirculated to slurry preparation.Raw biogas · 11,900–13,200 Nm³/day · 55–60% CH₄CBG dispatchLFOM recirculationFeedstockNapier grass · 115 TPDChopping & grindingSize reduction · conveyingSlurry preparationMixing · liquid recirculationCSTR DIGESTER1 × 10,000 m³ · mesophilicHRT ≈ 36 daysH₂S removalWater wash · iron oxyhydroxideCO₂ upgradingChilled water or 2-stage membraneGas dryingDesiccant · heatless regenerationCompressionReciprocating · odourisationCBG cascade filling≥ 98% CH₄ · up to 250 barPLC / SCADA · online gas quality monitoringSolid–liquid separationDigestate dewateringLFOMLiquid fraction · recirculatedFOMFermented organic manureRated CBG outputup to 5,000 kg/daydesign · 330 operating days/year
Schematic block diagram based on the DPR process configuration — not a plot layout or P&ID. Values are design figures, subject to final engineering.
Key systems

Digestion, compression and digestate recovery

Simplified illustrations of the main process systems in the plant design.

CSTR digester

Cross-section of a CSTR anaerobic digester showing slurry inlet, central mixer, gas collection space, raw biogas outlet and digestate outletSlurry inletDigestate outletRaw biogas outletGas collection spaceCentral mixingMesophilictemperature controlUniform, continuouslymixed slurryCSTR · 1 × 10,000 m³ (flagship design)

CBG cascade filling

Compressed biogas flows from the compressor into a manifold feeding a cascade of high-pressure cylinders, from which CBG is dispatchedFrom compressorodourised, driedgas ≥ 98% CH₄PICascade storage · design up to 250 barDispatch

FOM / LFOM separation

Digestate enters a solid–liquid separator; the solid fraction is discharged as FOM and the liquid fraction is collected as LFOM, partly recirculated to slurry preparationDigestateSolid–liquid separatorFOMsolid fractionLFOMliquid fractionPart recirculated to slurry preparation
Gas upgrading

Purification and upgrading configuration

Technologies specified in the DPR, supplied through technology partners.

H₂S removal

Water washing / scrubbing with iron oxyhydroxide media

Hydrogen sulphide is removed early in the gas train to protect downstream equipment from corrosion and to meet CBG quality limits.

CO₂ removal & methane upgrading

Chilled-water scrubbing or two-stage membrane separation

Carbon dioxide is separated from the gas stream to raise methane content from 55–60% in raw biogas to at least 98% in the product gas.

Gas drying

Desiccant dryer with heatless regeneration

Moisture is removed so the gas meets dew-point requirements before high-pressure compression and storage.

High-pressure compression

Reciprocating compressor, design up to 250 bar

Upgraded gas is compressed in stages for cascade storage and dispatch as compressed biogas.

Automation & gas quality

PLC / SCADA with online gas quality monitoring

Process parameters and product gas composition are monitored continuously for stable, safe and documented operation.

By-products

FOM & LFOM

Actual FOM and LFOM quantities and their marketable quality depend on feedstock, plant operation and final product specifications, including applicable fertiliser regulations.

Implementation approach

How the project will be delivered

Indicative equipment delivery is 36–42 weeks per the supplier's estimate, subject to conditions.

  1. 01

    Feedstock planning

    Napier grass cultivation and supply arrangements, with multi-feedstock flexibility to manage seasonal variation.

  2. 02

    Engineering & approvals

    Final process engineering, plot layout, statutory approvals and safety clearances for gas handling and storage.

  3. 03

    Technology & equipment

    Digester, gas upgrading, compression and filling systems delivered through specialist technology suppliers.

  4. 04

    Construction & erection

    Civil works, digester construction, mechanical erection, piping and electrical installation.

  5. 05

    Commissioning

    Biological start-up of the digester, gas-train commissioning and performance verification against design values.

  6. 06

    Operations

    Steady-state operation with feedstock logistics, gas quality monitoring, CBG dispatch and organic manure handling.

Project enquiries

Interested in the 5 TPD CBG project?

Feedstock suppliers, CBG off-takers, technology partners and organic manure buyers are welcome to contact us about the Shivni project.